Choreographing the I-25/Paseo project - Albuquerque Journal

Choreographing the I-25/Paseo project

Copyright © 2014 Albuquerque Journal

The signature element of the new Paseo del Norte/Interstate 25 interchange will be the flyover from northbound I-25 to westbound Paseo, shown here taking shape recently.  (Roberto E. Rosales/Albuquerque Journal)
The signature element of the new Paseo del Norte/Interstate 25 interchange will be the flyover from northbound I-25 to westbound Paseo, shown here taking shape recently. (Roberto E. Rosales/Albuquerque Journal)

Deploying about 380 workers and 214 pieces of equipment shift by shift on the reconstruction of the Paseo del Norte and Interstate 25 interchange is a hands-on affair at Kiewit New Mexico, general contractor for the project.

Roughly 40 superintendents and engineers gather at 1 p.m. daily for a half-hour in a 20-by-40-foot conference room, walls covered by magnetic dry-erase boards with handwritten logistics, at Kiewit’s headquarters at 5130 Masthead NE. Smartphones and laptops are unnecessary.

They work out the assignments for 50 crews, each with an average of five to six workers, for that evening’s shift and the next day’s shift with an eye on making sure the crews are efficient, effective and not working on top of one another, said Gray Kite, senior vice president and top executive of the New Mexico division.

“This is the heartbeat of the job,” he said about the daily meeting. “It’s the choreography of the job, what goes where.”

Born in Taos and raised in Cimarron, Kite has been with Kiewit for 31 years. He was involved in the Big I reconstruction, completed in 2002; the Coors and Interstate 40 interchange reconstruction, completed in 2006; and the RailRunner track extension in the Santa Fe area, completed in 2008.

Adding it up

The Paseo project will require shifting 29,000 dump-truck loads of fill dirt, erecting 160,400 square feet of retaining and sound walls, rehabbing two existing bridges, and laying 116,750 tons of hot-mix asphalt from Kiewit’s plant near the Big I, according to company numbers.

The project also calls for five new bridges, including its signature flyover for traffic northbound on I-25 to westbound on Paseo that’s currently going up. The first girders were trucked in from Little Rock, Ark., joined together on site and hoisted into place with two huge cranes this past weekend.

Other major bridges are the Paseo overpass at Jefferson and a southbound frontage road overpass to allow westbound traffic on Paseo to flow seamlessly to southbound I-25.

These three bridges will eliminate traffic lights that create congestion for commuters traveling from homes on the West Side to jobs on the east side of the river in the morning, then back again in the evening.

“Those are the main improvements, the direct connects to I-25,” Kite said.

The other traffic bridge is at the new braided ramp configuration for northbound lanes between San Mateo and San Antonio. The fifth bridge will be for pedestrians.

A small footprint

One of the challenges of the Paseo project is its comparatively small footprint, which is about one-fourth of the size of the Big I reconstruction footprint. Kite said about 70 percent of the work is taking place in a three-quarter-mile corridor from the interchange west to just past Jefferson.

While all this activity is underway, the Paseo interchange remains open for traffic during the critical rush hours, morning and evening. When the project started, traffic on Paseo at the interchange was approaching 155,000 vehicles a day, almost six times the traffic count in 1988, the year after the road opened.

“First and foremost, the safety of the traveling public is a priority,” Kite said. “Correct signage and correct lanes, all that stuff makes a huge impact on how successful the project is from a public perception.”

It almost seems ironic that the project has made Paseo a safer road to drive on.

“We’re having half as many accidents as there were prior to construction starting. That could be due to more signage, more lighting, slower speeds,” Kite said. “We had similar stats during the Big I project.”

Commercial discounts

The construction footprint of the Paseo/I-25 interchange project, shown here, is about one- fourth the size of the Big I rebuild of 2000-02, presenting its own unique set of challenges for general contractor Kiewit New Mexico.
The construction footprint of the Paseo/I-25 interchange project, shown here, is about one- fourth the size of the Big I rebuild of 2000-02, presenting its own unique set of challenges for general contractor Kiewit New Mexico.

The disruption in traffic caused by the project actually has created cost-saving opportunities for businesses in need of warehouse space.

Industrial real-estate brokers Mike Leach of Sycamore Associates and Jim Smith of CBRE either have marketed or are currently marketing space in the area north of Paseo/Jefferson with a special construction discount on rent through the end of the year. The discounts are offered only on long-term leases.

“The thought process was let’s cut people some slack if they want to be a tenant and cope with the congestion,” Smith said.

The 14-month construction project began in October after the Albuquerque International Balloon Fiesta concluded and is scheduled to end Dec. 20

“We’ll make that Dec. 20 date,” Kite said. “We have a lot of workforce out there, and we’re currently on track to beat that (date) a little bit. Things are coming along about as we expected them to.”

On face value, the $93 million Paseo project has taken place on a short timeline.

The New Mexico Department of Transportation put the project out for final bids in early June 2013 as a design/build contract. Kiewit submitted its final bid in mid-July 2013 and was awarded the $75 million construction contract at the beginning of August. Work began several weeks later.

Long time planning

In reality, Kite said Kiewit started preparations years ago to win the contract and build the project. Forecasts were developed for the needed manpower, equipment and material and where it all would come from. The actual bid solidified the forecasts.

Gray Kite, senior vice president of Kiewit New Mexico, explains how the work schedule is updated daily in a conference room at the company headquarters in the Journal Center area. From the 1940s until a rebranding in 2009, Kiewit operated as Twin Mountain in the state.
Gray Kite, senior vice president of Kiewit New Mexico, explains how the work schedule is updated daily in a conference room at the company headquarters in the Journal Center area. From the 1940s until a rebranding in 2009, Kiewit operated as Twin Mountain in the state.

By the time the contract is awarded, he said, “you pull the trigger and overnight sets it all in motion.”

Kiewit New Mexico is part of a network of decentralized offices of Omaha, Neb.-based Kiewit Corp., an employee-owned construction firm that dates back to 1884. As such, it can mobilize resources from across the country for a given project. For example, equipment for the Paseo project comes from as far away as Tampa, Fla.

“Probably 75 percent of our craft workforce are employees who have worked for Kiewit here in New Mexico many times over,” Kite said. “That helps when you start a new job (because) you’re not hiring a brand-new workforce.”

Kiewit employees get accustomed to traveling where their skills are needed. In 2009, for example, Kite said he spent nine months in New Orleans working on the $1 billion Gulf Intracoastal Waterway West Closure Complex, a post-Katrina storm-surge protection facility.

Kiewit teamed with Bohannon Huston, an Albuquerque engineering firm, on the Paseo project’s design and critical path schedule.

“From a coordination standpoint, the project is broken into multiple different disciplines – a roadway discipline, a drainage discipline, a walls discipline, a structures discipline and so on,” Kite said. “Each one of those disciplines is managed by multiple superintendents, engineers, foremen.”

The critical path schedule gets a detailed update every month, which is then broken into a three-week “look ahead” at the required construction activity. The three-week look ahead is reviewed weekly by the 40 or so superintendents and engineers. The daily meetings are the final step in managing the project.

The reconstruction of the Paseo/I-25 interchange is not a Kiewit project, Kite said, but a “community project that has many, many stakeholders.”

The stakeholders include the involved government entities – state of New Mexico, city of Albuquerque and Bernalillo County – as well as the motorists who use the road and businesses located near it.

“It takes everybody for a project like this to be successful,” he said. “Everybody is pulling in the same direction.”

 

Home » Business » Outlook » Choreographing the I-25/Paseo project

Insert Question Legislature form in Legis only stories




Albuquerque Journal and its reporters are committed to telling the stories of our community.

• Do you have a question you want someone to try to answer for you? Do you have a bright spot you want to share?
   We want to hear from you. Please email yourstory@abqjournal.com

taboola desktop

ABQjournal can get you answers in all pages

 

Questions about the Legislature?
Albuquerque Journal can get you answers
Email addresses are used solely for verification and to speed the verification process for repeat questioners.
1
We want to know what you think about business ...
Business
Your feedback will help us provide ... Your feedback will help us provide what you most want to see in the Albuquerque Journal.
2
State safety workers are investigating an 'incident' involving the ...
ABQnews Seeker
The Environment Department's Occupational Health and ... The Environment Department's Occupational Health and Safety Bureau is investigating an incident involving a crane at Intel's Rio Rancho plant. 
3
U.S.-Mexico's strained relationship in need of a reset
ABQnews Seeker
The U.S.-Mexico relationship needs a reset. ... The U.S.-Mexico relationship needs a reset. Relations were already strained when then-presidential c ...
4
Albuquerque junk removal company expands into pressure washing
ABQnews Seeker
A year after quitting their desk ... A year after quitting their desk jobs to start a junk removal company, Nathan Farmer and Brian Battaglia have added pressure washing to the ...
5
Stocks rise on Wall Street as bank fears ease ...
Most Recent Biz News
NEW YORK (AP) -- Stocks are ... NEW YORK (AP) -- Stocks are rising Wednesday as Wall Street shakes off a bit more of the fear that dominated it earlier this ...
6
$264M offered in Gulf oil sale held under climate ...
Energy
NEW ORLEANS (AP) -- Oil companies ... NEW ORLEANS (AP) -- Oil companies offered a combined $264 million for drilling rights in the Gulf of Mexico on Wednesday in a sale ...
7
US: Credit Suisse violates deal on rich clients' tax ...
Most Recent Biz News
GENEVA (AP) -- Credit Suisse violated ... GENEVA (AP) -- Credit Suisse violated a plea agreement with U.S. authorities by failing to report secret offshore accounts that wealthy Americans used to ...
8
Study: Los Alamos County is healthiest in New Mexico
ABQnews Seeker
The University of Wisconsin Population Health ... The University of Wisconsin Population Health Institute's annual County Health Rankings, which are supported by the Robert Wood Johnson Foundation, examine health outcomes and ...
9
Francisco Pallares is new director of business development at ...
ABQnews Seeker
BRIEFCASE: Spaceport America is the first purpose-built ... BRIEFCASE: Spaceport America is the first purpose-built commercial spaceport in the world.